Construction Schedule

Default owner-builder template — adjust dates, dependencies and contractors

Planning

ActivityStartEndTimeDurationContractorPredecessorStatusConfirmationAdjust
Finalize PlansAug 14, 1969Sep 3, 196920 dCompleteNot Sent
PermittingSep 3, 1969Sep 23, 196920 dCompleteNot Sent

Site Work

ActivityStartEndTimeDurationContractorPredecessorStatusConfirmationAdjust
Site ClearingSep 27, 1969Oct 3, 19696 dBayard Site ServicesCompleteConfirmed
Excavation & GradingOct 4, 1969Oct 13, 19699 dBayard Site ServicesCompleteConfirmed

Foundation

ActivityStartEndTimeDurationContractorPredecessorStatusConfirmationAdjust
Footings & Foundation WallsOct 15, 1969Nov 4, 196920 dGranite Edge FoundationsCompleteConfirmed
Floor SystemNov 5, 1969Nov 12, 19697 dGranite Edge FoundationsCompleteConfirmed

Framing

ActivityStartEndTimeDurationContractorPredecessorStatusConfirmationAdjust
Wall & Roof FramingNov 14, 1969Dec 10, 196926 dRiverbend FramingFloor SystemCompleteConfirmed

Dry-In

ActivityStartEndTimeDurationContractorPredecessorStatusConfirmationAdjust
RoofingDec 12, 1969Dec 20, 19698 dHilltop RoofingWall & Roof FramingCompleteConfirmed
Windows & Exterior DoorsDec 22, 1969Dec 28, 19696 dClearview WindowsCompleteConfirmed

Rough-In

ActivityStartEndTimeDurationContractorPredecessorStatusConfirmationAdjust
Electrical Rough-In

Panel on north wall. Owner to have plans onsite.

Jan 1, 1970Jan 4, 19708:00 AM–4:00 PM3 dABC ElectricWindows & Exterior DoorsIn ProgressConfirmed
Plumbing Rough-InJan 2, 1970Jan 6, 19707:30 AM–3:30 PM4 dSummit Plumbing Co.ScheduledNotification Sent
HVAC Rough-InJan 5, 1970Jan 10, 19708:00 AM–4:00 PM5 dCardinal HVACScheduledOwner Follow-Up Needed
Rough-In InspectionsJan 12, 1970Jan 12, 19709:00 AM0 dWilliamson CountyHVAC Rough-InScheduledNotification Sent

Insulation

ActivityStartEndTimeDurationContractorPredecessorStatusConfirmationAdjust
InsulationJan 15, 1970Jan 19, 19704 dEverseal InsulationRough-In InspectionsReadyNot Sent

Drywall

ActivityStartEndTimeDurationContractorPredecessorStatusConfirmationAdjust
Hang & Finish DrywallJan 22, 1970Feb 5, 197014 dMeadow DrywallInsulationNot StartedNot Sent

Interior Finishes

ActivityStartEndTimeDurationContractorPredecessorStatusConfirmationAdjust
Interior Trim & DoorsFeb 10, 1970Feb 26, 197016 dHang & Finish DrywallNot StartedNot Sent
Cabinet InstallationMar 2, 1970Mar 8, 19706 dOakline CabinetryNot StartedNot Sent
Flooring & TileMar 12, 1970Mar 30, 197018 dNot StartedNot Sent

Exterior

ActivityStartEndTimeDurationContractorPredecessorStatusConfirmationAdjust
Siding & Exterior TrimJan 25, 1970Feb 16, 197022 dNot StartedNot Sent
Driveway & LandscapingMay 1, 1970May 21, 197020 dNot StartedNot Sent

Final Inspections

ActivityStartEndTimeDurationContractorPredecessorStatusConfirmationAdjust
Final Inspections & COJun 18, 1970Jun 28, 197010 dNot StartedNot Sent