Planning
| Activity | Start | End | Time | Duration | Contractor | Predecessor | Status | Confirmation | Adjust |
|---|---|---|---|---|---|---|---|---|---|
| Finalize Plans | Aug 14, 1969 | Sep 3, 1969 | — | 20 d | — | — | Complete | Not Sent | |
| Permitting | Sep 3, 1969 | Sep 23, 1969 | — | 20 d | — | — | Complete | Not Sent |
Site Work
| Activity | Start | End | Time | Duration | Contractor | Predecessor | Status | Confirmation | Adjust |
|---|---|---|---|---|---|---|---|---|---|
| Site Clearing | Sep 27, 1969 | Oct 3, 1969 | — | 6 d | Bayard Site Services | — | Complete | Confirmed | |
| Excavation & Grading | Oct 4, 1969 | Oct 13, 1969 | — | 9 d | Bayard Site Services | — | Complete | Confirmed |
Foundation
| Activity | Start | End | Time | Duration | Contractor | Predecessor | Status | Confirmation | Adjust |
|---|---|---|---|---|---|---|---|---|---|
| Footings & Foundation Walls | Oct 15, 1969 | Nov 4, 1969 | — | 20 d | Granite Edge Foundations | — | Complete | Confirmed | |
| Floor System | Nov 5, 1969 | Nov 12, 1969 | — | 7 d | Granite Edge Foundations | — | Complete | Confirmed |
Framing
| Activity | Start | End | Time | Duration | Contractor | Predecessor | Status | Confirmation | Adjust |
|---|---|---|---|---|---|---|---|---|---|
| Wall & Roof Framing | Nov 14, 1969 | Dec 10, 1969 | — | 26 d | Riverbend Framing | Floor System | Complete | Confirmed |
Dry-In
| Activity | Start | End | Time | Duration | Contractor | Predecessor | Status | Confirmation | Adjust |
|---|---|---|---|---|---|---|---|---|---|
| Roofing | Dec 12, 1969 | Dec 20, 1969 | — | 8 d | Hilltop Roofing | Wall & Roof Framing | Complete | Confirmed | |
| Windows & Exterior Doors | Dec 22, 1969 | Dec 28, 1969 | — | 6 d | Clearview Windows | — | Complete | Confirmed |
Rough-In
| Activity | Start | End | Time | Duration | Contractor | Predecessor | Status | Confirmation | Adjust |
|---|---|---|---|---|---|---|---|---|---|
| Electrical Rough-In Panel on north wall. Owner to have plans onsite. | Jan 1, 1970 | Jan 4, 1970 | 8:00 AM–4:00 PM | 3 d | ABC Electric | Windows & Exterior Doors | In Progress | Confirmed | |
| Plumbing Rough-In | Jan 2, 1970 | Jan 6, 1970 | 7:30 AM–3:30 PM | 4 d | Summit Plumbing Co. | — | Scheduled | Notification Sent | |
| HVAC Rough-In | Jan 5, 1970 | Jan 10, 1970 | 8:00 AM–4:00 PM | 5 d | Cardinal HVAC | — | Scheduled | Owner Follow-Up Needed | |
| Rough-In Inspections | Jan 12, 1970 | Jan 12, 1970 | 9:00 AM | 0 d | Williamson County | HVAC Rough-In | Scheduled | Notification Sent |
Insulation
| Activity | Start | End | Time | Duration | Contractor | Predecessor | Status | Confirmation | Adjust |
|---|---|---|---|---|---|---|---|---|---|
| Insulation | Jan 15, 1970 | Jan 19, 1970 | — | 4 d | Everseal Insulation | Rough-In Inspections | Ready | Not Sent |
Drywall
| Activity | Start | End | Time | Duration | Contractor | Predecessor | Status | Confirmation | Adjust |
|---|---|---|---|---|---|---|---|---|---|
| Hang & Finish Drywall | Jan 22, 1970 | Feb 5, 1970 | — | 14 d | Meadow Drywall | Insulation | Not Started | Not Sent |
Interior Finishes
| Activity | Start | End | Time | Duration | Contractor | Predecessor | Status | Confirmation | Adjust |
|---|---|---|---|---|---|---|---|---|---|
| Interior Trim & Doors | Feb 10, 1970 | Feb 26, 1970 | — | 16 d | — | Hang & Finish Drywall | Not Started | Not Sent | |
| Cabinet Installation | Mar 2, 1970 | Mar 8, 1970 | — | 6 d | Oakline Cabinetry | — | Not Started | Not Sent | |
| Flooring & Tile | Mar 12, 1970 | Mar 30, 1970 | — | 18 d | — | — | Not Started | Not Sent |
Exterior
| Activity | Start | End | Time | Duration | Contractor | Predecessor | Status | Confirmation | Adjust |
|---|---|---|---|---|---|---|---|---|---|
| Siding & Exterior Trim | Jan 25, 1970 | Feb 16, 1970 | — | 22 d | — | — | Not Started | Not Sent | |
| Driveway & Landscaping | May 1, 1970 | May 21, 1970 | — | 20 d | — | — | Not Started | Not Sent |
Final Inspections
| Activity | Start | End | Time | Duration | Contractor | Predecessor | Status | Confirmation | Adjust |
|---|---|---|---|---|---|---|---|---|---|
| Final Inspections & CO | Jun 18, 1970 | Jun 28, 1970 | — | 10 d | — | — | Not Started | Not Sent |