Change Orders

Approvals flow straight into contracts, budget and forecast

Approved change orders

$1,800

Pending approval

$6,450

Total change orders

4

All change orders

#ContractorDescriptionReasonOriginal contractChangeNew contractRequestedSchedule impactStatus
CO-001Bayard Site ServicesAdditional tree removal and haul-offUnmarked trees inside build envelope$27,500$600$28,100Oct 1, 1969+1 dayApproved
CO-002Granite Edge FoundationsTwo extra courses of block at rear wallGrade change from survey$95,200$1,200$96,400Oct 29, 1969+2 daysApproved
CO-003ABC ElectricAdd EV charger circuit and garage subpanelOwner request$34,800$2,350$37,150Dec 30, 1969No impactReviewing
CO-004Cardinal HVACUpgrade to zoned system on second floorOwner request$38,900$4,100$43,000Dec 31, 1969+3 daysProposed