Passed
3
Scheduled
3
Corrections open
1
Not scheduled
3
Inspection tracker
| Inspection | Phase | Scheduled | Inspector | Result | Status | Notes | |
|---|---|---|---|---|---|---|---|
| Footing Inspection | Foundation | Oct 19, 1969 | Williamson County | Passed | Passed | — | |
| Foundation Inspection | Foundation | Nov 2, 1969 | Williamson County | Passed | Passed | — | |
| Underground Plumbing | Foundation | Nov 7, 1969 | Williamson County | Passed after reinspection | Passed After Reinspection | Cleanout added at rear wall. | |
| Framing Inspection | Framing | Dec 13, 1969 | Williamson County | Correction required | Correction Required | Add hurricane ties at 6 rafters — correction task created. | |
| Rough Electrical | Rough-In | Jan 12, 1970 | Williamson County | — | Scheduled | — | |
| Rough Plumbing | Rough-In | Jan 12, 1970 | Williamson County | — | Scheduled | — | |
| Rough HVAC | Rough-In | Jan 12, 1970 | Williamson County | — | Scheduled | — | |
| Insulation Inspection | Insulation | Jan 20, 1970 | Williamson County | — | Not Scheduled | — | |
| Final Building Inspection | Final | Jun 22, 1970 | Williamson County | — | Not Scheduled | — | |
| Certificate of Occupancy | Final | Jun 28, 1970 | Williamson County | — | Not Scheduled | — |