Owner Purchases

Materials and products you are buying directly

Budgeted

$177,400

Committed / spent

$127,900

Long-lead items

6

Orders at risk

2

Long-lead items at risk

Order by the recommended date to protect the schedule

APPLIANCE PACKAGE ORDER AT RISK

Required onsite: Apr 7, 1970

Estimated lead time: 14 weeks

Recommended order date: Dec 30, 1969

Current status: Selected

GARAGE DOORS ORDER AT RISK

Required onsite: Feb 22, 1970

Estimated lead time: 9 weeks

Recommended order date: Dec 21, 1969

Current status: Need Quote

All owner purchases

ItemCategorySupplier / modelQtyBudgetActualLeadOrder byNeeded onsiteExpectedStatus
Windows (whole house)WindowsClearview Windows

Series 400

28$46,800$46,80010 wkOct 13, 1969Dec 22, 1969Dec 20, 1969Installed
Appliance packageAppliancesFerguson

Café Suite

1$18,40014 wkDec 30, 1969Apr 7, 1970Selected
Kitchen cabinetsCabinetsOakline Cabinetry

Painted maple

1$52,400$52,40012 wkDec 8, 1969Mar 2, 1970Feb 28, 1970In Production
Plumbing fixturesPlumbing FixturesFerguson

Mixed

22$14,800$4,2006 wkFeb 6, 1970Mar 20, 1970Quoted
Interior lighting packageLightingLumens

Mixed

41$11,600$3,1005 wkFeb 15, 1970Mar 22, 1970Jan 31, 1970Ordered
Garage doorsGarage DoorsOverhead Door

Carriage 2-car

2$6,4009 wkDec 21, 1969Feb 22, 1970Need Quote
Tile — primary bathTileTile Shop

Calacatta 12x24

420$5,6008 wkFeb 2, 1970Mar 30, 1970Need Selection
HVAC equipmentHVACCardinal HVAC

16 SEER dual

2$21,400$21,4008 wkDec 6, 1969Jan 31, 1970Jan 21, 1970Ordered