Project Budget

Crawl Space foundation template · Custom Home

Original budget

$1,040,600

Current budget

$1,040,600

Change orders $0

Committed costs

$820,200

Paid to date

$483,620

46% of budget

Remaining

$556,980

Projected final cost

$1,040,600

Budget variance

$0

Contingency remaining

$32,200

Percentage of budget spent

46%

Preconstruction

8 lines · current $44,100

SubcategoryOriginalCurrentContractorContractChange ordersPaidRemainingForecastVarianceStatus
Land / Lot$0$0$0$0$0$0Under Budget
Survey$2,200$2,200Ridge Survey Group$2,200$2,200$0$2,200$0Near Budget
Soil Testing$1,400$1,400$1,400$1,400$0$1,400$0Near Budget
Architect$21,000$21,000Halstead Design$21,000$21,000$0$21,000$0Near Budget
Structural Engineer$6,800$6,800$6,800$6,800$0$6,800$0Near Budget
Permit Fees$5,400$5,400$5,400$5,400$0$5,400$0Near Budget
Impact Fees$3,100$3,100$3,100$3,100$0$3,100$0Near Budget
Builder's Risk Insurance$4,200$4,200$4,200$4,200$0$4,200$0Near Budget
Section total$44,100$44,100$44,100$0$44,100$0

Site Work

7 lines · current $36,600

SubcategoryOriginalCurrentContractorContractChange ordersPaidRemainingForecastVarianceStatus
Clearing$8,500$9,100Bayard Site Services$9,100$600$9,100$0$9,100$600Over Budget
Excavation$12,400$12,400Bayard Site Services$12,400$12,400$0$12,400$0Near Budget
Grading$6,800$6,800Bayard Site Services$6,800$3,400$3,400$6,800$0Under Budget
Erosion Control$1,800$1,800$1,800$1,800$0$1,800$0Near Budget
Temporary Power$1,500$1,500$1,500$1,500$0$1,500$0Near Budget
Dumpster$3,600$3,600$3,600$2,100$1,500$3,600$0Under Budget
Portable Toilet$1,400$1,400$1,400$800$600$1,400$0Under Budget
Section total$36,000$36,600$36,600$600$31,100$5,500

Utilities

4 lines · current $35,400

SubcategoryOriginalCurrentContractorContractChange ordersPaidRemainingForecastVarianceStatus
Septic$16,500$16,500$16,500$16,500$0$16,500$0Near Budget
Well$12,800$12,800$12,800$12,800$0$12,800$0Near Budget
Electric Service$4,900$4,900$4,900$4,900$0$4,900$0Near Budget
Internet / Communications$1,200$1,200$0$1,200$1,200$0Under Budget
Section total$35,400$35,400$34,200$0$34,200$1,200

Crawl Space Foundation

7 lines · current $88,400

SubcategoryOriginalCurrentContractorContractChange ordersPaidRemainingForecastVarianceStatus
Excavation$9,200$9,200Granite Edge Foundations$9,200$9,200$0$9,200$0Near Budget
Footings$14,800$14,800Granite Edge Foundations$14,800$14,800$0$14,800$0Near Budget
Block / Masonry$26,400$27,600Granite Edge Foundations$27,600$1,200$27,600$0$27,600$1,200Over Budget
Piers & Beams$11,200$11,200Granite Edge Foundations$11,200$11,200$0$11,200$0Near Budget
Floor System$18,600$18,600Granite Edge Foundations$18,600$18,600$0$18,600$0Near Budget
Vapor Barrier & Drainage$5,400$5,400Granite Edge Foundations$5,400$5,400$0$5,400$0Near Budget
Termite Treatment$1,600$1,600$1,600$1,600$0$1,600$0Near Budget
Section total$87,200$88,400$88,400$1,200$88,400$0

Framing

4 lines · current $188,200

SubcategoryOriginalCurrentContractorContractChange ordersPaidRemainingForecastVarianceStatus
Lumber Package$84,000$84,000Timberline Supply$84,000$84,000$0$84,000$0Near Budget
Trusses$21,500$21,500Timberline Supply$21,500$21,500$0$21,500$0Near Budget
Framing Labor$78,500$78,500Riverbend Framing$78,500$62,000$16,500$78,500$0Under Budget
Hardware / Fasteners$4,200$4,200$4,200$3,900$300$4,200$0Near Budget
Section total$188,200$188,200$188,200$0$171,400$16,800

Dry-In

4 lines · current $92,600

SubcategoryOriginalCurrentContractorContractChange ordersPaidRemainingForecastVarianceStatus
Roofing$29,600$29,600Hilltop Roofing$29,600$29,600$0$29,600$0Near Budget
Windows$46,800$46,800Clearview Windows$46,800$23,400$23,400$46,800$0Under Budget
Exterior Doors$12,400$12,400Clearview Windows$12,400$6,200$6,200$12,400$0Under Budget
House Wrap & Flashing$3,800$3,800$3,800$3,800$0$3,800$0Near Budget
Section total$92,600$92,600$92,600$0$63,000$29,600

Mechanical Rough-In

4 lines · current $121,300

SubcategoryOriginalCurrentContractorContractChange ordersPaidRemainingForecastVarianceStatus
Electrical$34,800$34,800ABC Electric$34,800$12,000$22,800$34,800$0Under Budget
Plumbing$41,200$41,200Summit Plumbing Co.$41,200$15,000$26,200$41,200$0Under Budget
HVAC$38,900$38,900Cardinal HVAC$38,900$0$38,900$38,900$0Under Budget
Low Voltage / Security$6,400$6,400$6,400$0$6,400$6,400$0Under Budget
Section total$121,300$121,300$121,300$0$27,000$94,300

Interior Construction

8 lines · current $217,200

SubcategoryOriginalCurrentContractorContractChange ordersPaidRemainingForecastVarianceStatus
Insulation$14,200$14,200$14,200$0$14,200$14,200$0Under Budget
Drywall$27,400$27,400Meadow Drywall$27,400$0$27,400$27,400$0Under Budget
Interior Doors & Trim$22,800$22,800$22,800$0$22,800$22,800$0Under Budget
Cabinets$52,400$52,400Oakline Cabinetry$52,400$15,720$36,680$52,400$0Under Budget
Countertops$18,600$18,600$0$18,600$18,600$0Under Budget
Tile$16,400$16,400$0$16,400$16,400$0Under Budget
Flooring$43,600$43,600$0$43,600$43,600$0Under Budget
Painting$21,800$21,800$0$21,800$21,800$0Under Budget
Section total$217,200$217,200$116,800$0$15,720$201,480

Exterior

4 lines · current $84,400

SubcategoryOriginalCurrentContractorContractChange ordersPaidRemainingForecastVarianceStatus
Siding$34,500$34,500$34,500$0$34,500$34,500$0Under Budget
Brick / Stone$28,900$28,900$28,900$0$28,900$28,900$0Under Budget
Gutters$4,200$4,200$0$4,200$4,200$0Under Budget
Decks / Porches$16,800$16,800$0$16,800$16,800$0Under Budget
Section total$84,400$84,400$63,400$0$0$84,400

Fixtures & Finishes

4 lines · current $48,600

SubcategoryOriginalCurrentContractorContractChange ordersPaidRemainingForecastVarianceStatus
Plumbing Fixtures$14,800$14,800$4,200$10,600$14,800$0Under Budget
Lighting$11,600$11,600$3,100$8,500$11,600$0Under Budget
Appliances$18,400$18,400$0$18,400$18,400$0Under Budget
Door Hardware$3,800$3,800$0$3,800$3,800$0Under Budget
Section total$48,600$48,600$0$0$7,300$41,300

Exterior Completion

3 lines · current $43,400

SubcategoryOriginalCurrentContractorContractChange ordersPaidRemainingForecastVarianceStatus
Driveway$18,200$18,200$0$18,200$18,200$0Under Budget
Landscaping$18,400$18,400$0$18,400$18,400$0Under Budget
Irrigation$6,800$6,800$0$6,800$6,800$0Under Budget
Section total$43,400$43,400$0$0$0$43,400

Final

4 lines · current $40,400

SubcategoryOriginalCurrentContractorContractChange ordersPaidRemainingForecastVarianceStatus
Final Cleaning$1,800$1,800$0$1,800$1,800$0Under Budget
Inspections$2,400$2,400$2,400$1,400$1,000$2,400$0Under Budget
Punch List$4,000$4,000$0$4,000$4,000$0Under Budget
Contingency$34,000$32,200$32,200-$1,800$0$32,200$32,200-$1,800Under Budget
Section total$42,200$40,400$34,600-$1,800$1,400$39,000